Works between Pagram Way and Milton Road have been completed ahead of schedule. The Guided Busway and adjacent path reopened on Sunday 23 August 2026 prior to the start of the academic year at Cambridge Regional College.
As sections of safety works are completed along the Guided Busway, our Busway safety officers review and monitor the area to review and assess changes in behaviour in reaction to the new fencing. Where it is safe to do so, we will look to lift speed limits on the Busway once safety measures are working effectively. We continue to work with Cambridgeshire Constabulary to tackle anti-social and illegal behaviour along the route.
Works between Milton Road and Cambridge North Station will begin in mid-September and are anticipated to take around eight weeks. We plan to continue to install the green coloured ‘weld mesh’ fencing along this section of the route.
During the work between Milton Road and Cambridge North Station, access will be maintained for buses throughout the works. Buses will not be diverted. As in other sections, the path will remain open for use by pedestrians, cyclists and Voi e-scooter users. We ask that everyone share the space with care, as the path will be narrower than usual while works are taking place.