Orchard Park to Milton Road works continue with fencing being installed between Orchard Park and Cambridge Regional College. Works start soon to install separation fencing between the College and Milton Road. As well as separation fencing between the path and the Busway, perimeter fencing is being installed between Garry drive and the Busway track. The closure of the Busway track remains in place in this area. The path is open to pedestrians and cyclists.
The A bus service uses the route via Orchard Park. B Buses are diverted around the closure via Kings Hedges Road and Milton Road and continue to serve Cambridge North Station in both directions.
The following alternative stops are available for the B bus:
For Cambridge Regional College, please use Orchard Park West stops
In place of Histon & Impington stop city-bound, services depart from the number 8 bus stop near the shop (the existing St Ives bound stop on the Busway remains open).
The alternative stop for Cambridge Science Park is on Milton Road outside the car dealership and on the opposite side of the road (what3words /// chair.palace.intelligible).
The bus continues to serve Milton Road. It stops outside the Golden Hind and uses the new style bus stop diagonally opposite (what3words /// crisis.chips.outfit).
On the southern section, works have started at the Addenbrookes Spur junction and are progressing well. Temporary traffic lights are in place, but this is not causing noticeable delays services. Work on the junction is expected to be completed in mid-June.
Works are ongoing to install the bespoke panels of railings along the sections where separation fencing has been installed on both the northern and southern sections. In the southern section, this work is due to be completed in mid-June.
All works between Cambridge Station and Trumpington Park & Ride should finish in late June. We would like to thank everyone for their patience throughout the works.