The installation of separation fencing continues to progress well on the southern section of the Busway, at the Trumpington Spur and from Pagram Way to Histon.
We expect to complete the Trumpington Spur fencing and reopen this section at the end of February. The work from Pagram Way to Histon will be finished by the end of March.
With the progress on the southern section of the Busway fencing, we expect to start works on the Addenbrookes Spur at the beginning of March and be completed around the beginning of May 2026.
We are currently finalising the planned diversions for this section of the route. The maintenance track, the path alongside the busway, will be closed to cyclists and pedestrians during the work and a signed diversion will be in place.
Further details will be shared ahead of the start of the works.
We apologise for the inconvenience and urge those travelling to Addenbrookes and the Cambridge Biomedical Campus to plan their journeys in advance.